By Tracy Record
West Seattle Blog editor
Two major updates on the first Fauntleroy Creek culvert project emerged at a community meeting last night: A contractor’s been chosen, and major construction might start later next year than anticipated.
Seattle Public Utilities is leading the projects to replace and expand culverts that carry the salmon-bearing creek between Fauntleroy Cove and Fauntleroy Park. The first to be replaced goes under 45th SW north of the Endolyne business district; the second goes under California SW and the Fauntleroy Church parking lot, near Fauntleroy Schoolhouse.
The schoolhouse is where project manager Justin Record, outreach coordinator Anny Chang, and engineer Tracey Belding met with ~20 community members last night.
“We’re getting ready to do what we’ve been planning to do for a very long time,” said Record, describing himself as a relative newcomer to SPU, taking over the project from its previous manager. He recapped the 45th SW culvert project, which has been in the planning phase for ~10 years and will close 45th for up to two years: A two-foot-wide culvert with a “bulge” inside “needs to be replaced… repair is not an option, waiting is not an option.” The new culvert will “restore and improve fish passage” and also will improve working conditions for SPU’s crews so they can better maintain it – the old one is a challenge to maintain.
“Early work” has been under way since summer and is expected to conclude by month’s end.
Some of the vaults they’re installing are for handling creek water while the culvert is being replaced. One attendee asked about poles; City Light will restring wire when the SPU work is complete. “There will be short outages” with advance notice, Belding said. Record showed photos from the work and also an image of “sheet piles” that will be installed, “nearly vertical construction …. that’s how we dig a nearly 40-foot culvert in such a small site.” Some will be drilled in rather than pounded in.
Showing an overview of the site, he warned that some trees would be removed; new trees would be planted.
The finished culvert will be 14 feet wide and 9 feet tall. The bottom of the culvert will be like a stream bed, to help the fish feel more comfortable with it.
As for how construction will affect the streets: There’ll be a four-way stop where Barton turns into California just north of the schoolhouse. The roundabout at 45th/Director will be removed, partly because truck access will be needed. Will it change back? Record said that’s up to SDOT, which was not represented at the meeting. Other traffic-related questions followed but he repeated that SDOT had the ultimate jurisdiction.
Also from Q&A:
Is the California Avenue culvert going to happen? Record said planning and design continue (and said several times during the meeting that the California SW project would not start until the 45th project was done). It’s currently up to the 30 percent design phase.
What should Wildwood Market – in the heart of this project zone – be telling delivery drivers? “Provisions in the contract (say) they have to coordinate with you,” Belding said. The contractor and business would need to meet right before construction, she said. Parking for businesses in the area is yet to be worked out, the team said in response to another question.
That’s where Record mentioned that the city had just signed a contractor “a few days ago” – C.A. Carey. (They’ve worked on West Seattle projects before, our archive shows, including one on the west end of the West Seattle Bridge.) We checked the city’s bidding website; the contract finalized last Friday is for $19.3 million.
He also said that during construction, there’ll be cranes on site, and other heavy equipment. Noisiest phase will be sheet pilings installation and excavation. The road closure is two years maximum, so the contractor has to plan how to get it all done. Work can start as early as 7 am.
As for the timeline, that’s when he revealed the most intensive work is likely to start later than previously projected – because the contractor is likely to have a “long lead time” for materials, particularly the sheet pile and steel – so the actual culvert construction might be more like a summer/fall start.
Is there a fish window (when work can’t be done)? No, since fish can’t get through now, Record said – the contractor will be able to work nonstop.
Is the 45th closure planned to be a complete street shutdown? You can access existing buildings from either side, he said. They’ll meet with buildings’ reps when everything gets closer and the contractor is more ramped up.
A resident asked for signage to dissuade cut-throughs on 43rd and 44th off Director.
Shortly afterward, the meeting wrapped up but team members lingered for one-on-one discussion. If you have project questions, Record’s contact information is on this project webpage. He promised SPU would continue communicating with the community in a variety of ways, including an email list to which you can subscribe via that same webpage.